Why Land Is Taking Longer to Title in WA and How to Plan Around It

An Image of WA Land, Showcasing the Titling Delays and What Buyers Need to Know

Not long ago, buying a house and land package in Perth was simple. Choose a titled lot, settle within weeks, and start building.

Builders say that has changed. Developers are now selling lots three, six, nine or twelve months before they title, and some are further out. If you are planning a Perth build, the timeline matters as much as the price.

What Does “Titled” Mean?

Land is titled once the new lot has been formally created and registered. Until then, you can sign a contract and pay a deposit, but you cannot settle or start building.

Buying untitled land is common in other states. South Australia, for example, has long had buyers holding land for 12 to 18 months before it titles. It is newer for WA buyers, who were used to a steady supply of ready lots.

Why Is It Happening?

Titled land has largely run out, and developers are selling ahead of titling. Civil works need to be completed before land is registered, and contractor capacity is stretched. When a developer sells ahead, the buyer carries the wait.

What Does the Timeline Look Like?

A typical journey now looks like this:

  1. Sign the land contract and pay a deposit

  2. Wait for titling, which may be 3 to 15 months

  3. Settle on the land and begin pre-construction

  4. Build, which can take 6 to 12 months or longer

From signing to keys, the whole journey can stretch toward two years. Brick supply issues can add further delay to the build stage.

Is There an Upside?

Yes, for the right buyer.

You typically pay only a deposit until the land titles. Builders report deposits of around 5%, or $10,000 to $15,000, on some lots. Some young buyers use this window to lock in a lot while their income grows, planning to qualify for finance by settlement.

What Are the Risks?

Finance can change. Rates and lending rules move. Your approval today may not match your position at settlement.

Values can move. You may settle on a lot priced above or below the market.

No income until built. Investors earn no rent until the home is complete.

Delays happen. Titling dates are estimates.

Questions to Ask Before You Sign

  • What is the estimated titling date and how reliable has it been?

  • What does the contract say if titling is delayed? Is there a sunset clause?

  • How is my deposit held and protected?

  • How long is the gap between titling and a builder start?

  • Is my finance approval timed to settlement?

Have your conveyancer review any contract before you sign.

Planning a Perth build?

Motivate Property Group can help you map the timeline. Book a free consultation at today to map our your personalised strategy.

Frequently Asked Questions

Do I pay interest before the land titles?
Typically not. Settlement happens after titling, so you generally pay the deposit only. Confirm this in your contract.

How long does land take to title in Perth?
It varies by project. Builders are seeing lots sold from three months to over a year out.

Is buying untitled land a good idea for investors?
It can work, but you will not earn rent until the home is built. Model the full timeline and holding costs first.

Disclaimer: This article provides general information only and does not constitute financial, legal or investment advice. Always seek independent advice and have a conveyancer review contracts.